The Risk Assessment Code is the one line on an activity hazard analysis that every reviewer reads first. It tells the contracting officer's representative how much risk is left once your controls are in place, and it decides who has to accept that risk before work starts. Get it wrong in either direction and the AHA comes back. This post covers how the matrix works under the 2024 edition of EM 385-1-1, how to rate each job step, how to set the overall RAC, and the mistakes that most often get an AHA returned.
The matrix: severity against probability
A RAC is read off a grid. One axis is severity, the outcome if a mishap occurs. The other is probability, the likelihood that the activity causes a mishap. Where they cross, you get one of four letters. EM 385-1-1 (2024), Chapter 2, defines the terms; the grid itself is the one on ENG Form 6206, the non-mandatory AHA format the manual points to.
| Severity \ Probability | Frequent | Likely | Occasional | Seldom | Unlikely |
|---|---|---|---|---|---|
| Catastrophic | E | E | H | H | M |
| Critical | E | H | H | M | L |
| Moderate | H | M | M | L | L |
| Negligible | M | L | L | L | L |
E is Extremely High Risk, H is High Risk, M is Medium Risk, and L is Low Risk.
Use the 2024 words: Moderate and Medium
The grid did not change in the 2024 edition. The vocabulary did. The manual names the four severities catastrophic, critical, moderate, and negligible, and the four risk levels extremely high, high, medium, and low. Many contractor forms still print Marginal for the third severity and Moderate Risk for M, carried over from the previous edition.
That matters more than it looks. On an old form, “Moderate” was a risk level. On a 2024-edition AHA it is a severity. A reviewer who sees “Moderate” in the RAC column has to guess which one you meant. Update the form: Moderate is a severity, Medium is a risk level. For the rest of what changed, see what changed in the 2024 edition.
Rate every job step, after controls
Chapter 2 asks for a RAC on each job step, and it is specific about which risk you are rating: the residual risk that remains after controls have been applied. Rating the uncontrolled hazard is the most common reason a RAC looks wrong. A trench with no protective system is catastrophic and likely; nobody writes an AHA for that trench. You write it for the trench with a trench box, a competent person, and a ladder within reach.
A practical way to rate a step:
- Set severity from the hazard. Ask what the worst credible outcome is if this hazard is realized. A fall from a roof edge is catastrophic whether or not there is a guardrail. Controls rarely change the consequence; they change the likelihood.
- Set probability from the controls. Ask how likely the mishap is with your listed controls in place. This is where the hierarchy of controls shows up in the number.
- Read the letter off the grid. Do not pick a letter first and work backwards.
The manual also asks you to keep adding controls until the residual risk is acceptable, which it describes as low or medium where possible. If a step is still H after your controls, either the controls need another layer or the step genuinely carries high risk and needs acceptance at that level.
The overall RAC is the highest step, never lower
The overall RAC goes at the top of the AHA. Chapter 2 sets one rule for it: it must not be lower than the highest job-step RAC. Sixteen steps rated L and one rated H make an H activity. Averaging is not allowed, and neither is rating the activity on its “typical” step.
The overall RAC also drives acceptance. Prime contractors set out in their APP who may accept each level of residual risk, and the AHA cannot start until that person has accepted it. If a later change raises the RAC, the AHA goes back for acceptance before work resumes.
What reviewers send back
- RAC too low for the controls listed. A catastrophic hazard rated Unlikely with nothing but training and PPE listed. PPE and briefings are the weakest controls. Unless something physical stands between the worker and the hazard (a guardrail, shoring, an isolated energy source, an exclusion zone), Unlikely is hard to defend.
- Severity lowered by controls. Dropping a roof-edge fall from catastrophic to moderate because the crew wears harnesses. The harness changes the probability, not what a fall would do.
- No visible rationale. A letter with no hazard or control that explains it. If the controls column is thin, the RAC has nothing to stand on.
- Overall RAC lower than a step. Usually a copy-and-paste header from another AHA.
- Old wording. Marginal and Moderate Risk on a 2024-edition contract.
How AHA Generator assigns RAC
The generator splits the job between the model and the code. For each job step the model proposes a severity and a probability under written rules. Severity is the consequence if the hazard is realized, with controls set aside. Probability is the residual likelihood, and it follows the kind of controls listed: an engineering, substitution, or elimination control can support Unlikely on a high-severity step, while administrative and PPE controls alone cannot.
The model never sets the letter. The code reads every RAC off the matrix above, using the 2024 words. A check then runs on every step: a catastrophic or critical step with no elimination, substitution, or engineering control may not be rated Unlikely, and is raised to Seldom. A response with a severity or probability that is not on the matrix is rejected and generated again, rather than saved with a guessed letter. The overall RAC fills itself in from the highest step RAC, so it cannot sit below a step.
You still review every step. The job steps, hazards, and controls are editable before you save, and your competent person should read the RAC against the controls as a reviewer would.
Try it on your next activity
Your first AHA is free, and no credit card is required. Pick an activity, review the job steps and controls, and download it as Word or PDF. See what a finished document looks like in the complete sample AHA.