❄️ Winter Work AHAs: Cold Stress, Ice, Temporary Heat and CO

Posted on: 21 November 2026

The activity hazard analysis you wrote in September for setting forms, hanging drywall, or pulling wire was written for September. Once the temperature drops, the same activity has new hazards: workers losing body heat, ice on the ladder rungs, a propane heater running inside a tarped enclosure, and crews finishing the shift in the dark. EM 385-1-1 (2024), Chapter 2, requires the AHA to be modified as needed to address changing site conditions. Winter is a changing site condition. Here is what to add.

Cold stress and wind chill

Chapter 6 of the 2024 manual defines cold stress as the cold-related illnesses that occur when the body can no longer maintain its normal temperature, ranging from mild and treatable to permanent tissue damage and death. It treats heat and cold together as thermal stress, and it references the Army's TB MED 508 on preventing cold weather injuries.

Air temperature alone understates the risk: wind, wet clothing, and cold metal all pull heat from the body faster. Practical controls for the AHA:

Ice and snow on walking and working surfaces

Chapter 24, Safe Access, requires means of access to be kept clear of hazards, with ice named as one of them, and abrasive material applied where access is slippery. Ice and snow also make every roof and edge more dangerous, so recheck the Chapter 21 fall protection controls before winter work at height. Add a step at the start of each shift to clear and treat stairs, ladders, scaffold platforms, ramps, and walkways before anyone uses them, and name who does it. Watch for snow hiding openings, cords, and material on the deck. For excavations, Chapter 25 lists freezing weather among the factors that affect slope stability; a thaw after a hard freeze needs a fresh look from the competent person.

Haul roads count too. Chapter 5 asks for high-visibility apparel suited to reduced visibility, including snow, and the manual asks for site roads to be kept free of hazards such as ice and ruts.

Temporary heaters and carbon monoxide

This is the winter hazard that most often catches crews indoors. A fuel-fired heater burns oxygen and produces carbon monoxide, an odorless gas that a worker cannot detect without a meter. Enclosures built to hold heat also hold CO. Chapter 9, Fire Prevention and Protection, sets out the rules for temporary heating devices, including:

OSHA's construction rules cover the same ground under 29 CFR 1926 Subpart F, Fire Protection and Prevention. On the AHA, add a CO monitoring control for any enclosure with a fuel-fired heater or engine, name who reads the meter and how often, and say what happens on an alarm: stop work, leave, ventilate, find the source.

Fuel storage and refueling

Winter brings more fuel onto site. Store cylinders upright, secured, and outside enclosures. Keep fuel away from heaters and ignition sources, keep fire extinguishers where the heaters are, and shut down fuel-burning equipment before refueling it. Chapter 9 covers fire extinguisher distribution, and Chapter 14 covers dispensing flammable liquids and shutting equipment down to refuel it.

Cold-weather concrete

Pours in cold weather usually mean blankets, tented enclosures, and heaters running overnight to protect the curing concrete. That combines several of the hazards above in one place. If the enclosure is heated with a fuel-fired heater, the heater and CO controls apply. Add controls for checking the enclosure before re-entry, for tarps and framing loaded by wind and snow, and for the slip hazard of curing compound and frost on the slab. Chapter 27 covers concrete work generally.

Shorter daylight

Shifts that started in daylight in summer now end in the dark. Chapter 7, Lighting, sets minimum lighting for work areas, and the Energy Wheel supporting-plans checklist includes a Lighting Plan. Add temporary lighting at access routes, laydown areas, and the parking lot, and plan the end of the shift so the last task is not a lift or an edge task in fading light.

Equipment cold starts

Batteries fail, hydraulic oil thickens, and windshields and steps ice over. Operators should allow warm-up time, clear glass and mirrors fully, and clean ice from steps and grab handles before climbing on. Chapter 16 has crane manufacturers publish operating limits for cold weather; check them before the first lift of a cold morning.

Example: adding winter rows to an existing AHA

Here is what a winter update might add to an interior framing AHA in a building with temporary heat:

Job stepHazardControls
Access building at shift startSlip on ice at entry stairs and rampForeman clears and applies abrasive before crew arrives; slip-resistant footwear required; lighting at entry
Operate temporary heaterCarbon monoxide build-up; fire from heater clearanceHeater approved by COR before use; vented to exterior per data plate; clearances kept; CO meter in the work area, read and logged by the SSHO each hour
Refuel heaterFuel release and fireHeater shut down and cooled; trained worker only; extinguisher within reach; cylinders stored outside
Exterior work at loading dockCold stress from wind and wetWarm-up shelter; scheduled breaks; buddy checks; dry spare gloves

Rate each new row with a RAC, recheck the overall RAC, and remember the rule from Chapter 2: if the overall RAC goes up, the AHA goes back for acceptance before work continues. Either way, the crew reviews and signs the revision before they start. See who signs an AHA for when the crew signs again.

Updating a winter AHA in AHA Generator

Reopen a saved AHA, add or edit job steps, hazards, and controls for the winter conditions, and save it as a new document. The old version's crew sign-off link closes, so anyone who scans the old printout is told the AHA has been revised. The new version prints its own QR codes, and the crew signs again from their phones.

Try it on your next activity

Your first AHA is free, and no credit card is required. Pick an activity, review the job steps and controls, and download it as Word or PDF.

Generate a free AHA: start here